Why most Short Interval Control sandwiches fail

 In our experience, most SIC sandwiches don’t work because of weakness in the top two layers.

Without a reasonable and agreed shift plan, the crew doesn’t have realistic targets to aim for, so there is no point breaking those targets up into smaller intervals to track against. “But”, you say, “we have the weekly plan (from Deswik, EPS or Xact etc.) which sets the targets.” Dividing a weekly production plan target into 14 even shifts is a convenient and easy shortcut to take but is destined for failure because it doesn’t take into account the variability in the workplace (conditions, maintenance, sick leave etc.) that the supervisor has to cope with.

Dividing the week up into shifts without taking all the other work and conditions into account means the supervisor and crew will never have a plan that actually makes sense on their shift – some shifts will have low targets and others will have unachievable targets, there will be services or sequence work that needs to be done and machines will need to be maintained, making the plan impossible.

Send a crew to work over and over again with a plan that doesn’t make sense and it’s likely they will lose respect for the plan (and their leaders) and choose to do things their own way.

Making SIC work

The holy grail of SIC is to have a single system that enables you to bring all planning information into an integrated shift plan that can be agreed at weekly and daily commitment meetings. This plan can then be:

  • reviewed, adapted and committed to before the crew go to work
  • used to assign work to people
  • used to brief the crew at pre-starts/line-ups.

The same system can either print or deliver the plan to supervisors or crew on a phone or tablet at the face, and throughout the shift the work being done can be “closed off” in short intervals so that the control room, general foreman, shift boss, undermanager etc. and planners know that the right work is getting done.

This can integrate with fleet management systems to bring real-time data back to the supervisor through a tool, or regular radio calls can be made to check in on progress. At the end of shift, the supervisor and crew will have closed out most of the tasks and already written most of their shift report in the app, so a quick conversation around a touchscreen is enough to close out the shift.

All the data collected ends up in simple reports for use in daily review meetings to identify variances and plan corrective actions. This data is then available to business improvement people for analysis and continuous improvement work.



Commit Works has the only enterprise-quality system that makes this possible. It can be set up and implemented on your site in a matter of weeks and fits easily into operational expense budgets.

Global examples

Anglo Dawson OC, whiteboard daily planning meeting to set targets for the shift, paper based A3 SIC sheets, radio calls to each machine and supervisor at 3 hour intervals to say whether they were on plan or not.

Glencore Sudbury, UG Nickel mine planning development sequence work and tracking actuals from the face using an offline app.

Rio Kestrel, Fewzion work management planning system, crib room PC for entering actuals data, view of SCADA system and work orders from trades to tell how shift was progressing.

Anglo, Zibulo – Fewzion work management system, underground WiFi phones with a Fewzion Short Interval Control App to record actuals at the face.